Research on Anchorless Support for the Surge Shaft of Suki Kinari Hydropower Station

ZHAO Jianli1,2, HAO Xuehang1,2, YU Yang1, LI Pengcheng3, GAO Huamin4   

  1. 1. China Water Resources Bei Fang Investigation, Design and Research Co., Ltd., 300222, Tianjin, China;
    2. School of Water Resources and Hydropower, Hohai University, 210013, Nanjing, Jiangsu, China;
    3. Cangzhou Remote Sensing and Intelligent Water Conservancy Technology Innovation Center, Hebei University of Water Resources and Electric Engineering, 061001, Cangzhou, Hebei, China;
    4. Shandong Xinhui Construction Group Co., Ltd., 257000, Dongying, Shandong, China
  • Received:2023-11-22 Revised:2024-03-18 Online:2024-09-30 Published:2024-10-09

苏基克纳里水电站调压竖井无锚支护研究

赵建利1,2, 郝雪航1,2, 余洋1, 李鹏程3, 高华民4   

  1. 1.中水北方勘测设计研究有限责任公司,天津市河西区洞庭路60号 300222;
    2.河海大学水利水电学院,江苏省南京市鼓楼区西康路1号 210013;
    3.河北水利电力学院沧州市遥感与智慧水利技术创新中心,河北省沧州市黄河西路49号 061001;
    4.山东新汇建设集团有限责任公司,山东省东营市东营区胶州路532-1号 257000
  • 作者简介:赵建利(1990-),男,河北沧州人,工程师,硕士,主要从事水利工程规划与设计研究,E-mail:997974261@qq.com
  • 基金资助:
    河北省高等学校科学技术研究资助项目(BJ2021256);教育部第二期供需对接就业育人项目(20230113517、20230113516)

Abstract: Taking the pressure regulating shaft of the Suki Kinari project in Pakistan as an example, this article explores the feasibility and safety of anchorless support for Q4 and Q5 surrounding rock of vertical shafts, namely steel reinforced concrete support measures in practical engineering. The finite difference software FLAC3D is used to establish a three-dimensional model and numerical analysis of the excavation support process of the project, and the stress state of the sprayed concrete and steel is calculated to achieve good anchorless support results. The monitoring of the construction shaft during the construction period shows that this support method is safe and reliable, reduces construction procedures, saves project investment, and provides valuable reference for other similar projects.

Key words: shaft, anchorless support, FLAC3D, section steel

摘要: 文中以巴基斯坦苏基克纳里调压竖井为例,探讨竖井Q4类围岩和Q5类围岩的无锚支护形式,即型钢加喷混凝土支护措施在实际工程中的可行性和安全性,利用有限差分软件FLAC3D对该工程开挖支护过程进行三维模型建立及数值分析,并通过计算得到加喷混凝土及型钢的受力状态,取得较好的无锚支护结果。施工期对施工竖井的监测显示,该支护方式安全可靠,施工工序减少,工程投资节省,也为其他类似工程提供了有价值参考。

关键词: 竖井, 无锚支护, FLAC3D, 型钢