河北水利电力学院学报 ›› 2023, Vol. 33 ›› Issue (4): 38-41.DOI: 10.16046/j.cnki.issn2096-5680.2023.04.007

• 电气工程专题 • 上一篇    下一篇

单回路T接角钢塔在110kV输电线路设计中的应用

李乾飞1, 马丽2,3   

  1. 1.璞信电力工程设计有限公司,湖北省武汉市光谷大道3号 430040;
    2.河北水利电力学院电力工程系,河北省沧州市黄河西路49号 061001;
    3.河北省工业机械手控制与可靠性技术创新中心,河北省沧州市黄河西路49号 061001
  • 收稿日期:2023-05-08 修回日期:2023-10-17 出版日期:2023-12-30 发布日期:2024-01-12
  • 作者简介:李乾飞(1989-),男,河北邯郸人,工程师,主要研究方向为高压输电线路设计。E-mail:yueeryuanle@qq.com
  • 基金资助:
    河北水利电力学院2022年度基本科研业务费研究项目(SYKY2215)

Application of Single-circuit T Angle Steel Tower in 110kV Transmission Line Design

Li Qian-fei1, Ma Li2,3   

  1. 1. Puxin Electric Power Engineering Design Co., Ltd., 430040, Wuhan, Hubei, China;
    2. Department of Electric Engineering,HeBei University of Water Resourcesand Electric Engineering,061000,CangZhou,HeBei,China;
    3. Industrial Manipulator Control and Reliability Technology Innovation Center of Hebei, 061001, Cangzhou, Hebei, China
  • Received:2023-05-08 Revised:2023-10-17 Online:2023-12-30 Published:2024-01-12

摘要: 结合实际工程,介绍了110kV架空输电线路设计中,采用单回路耐张角钢塔进行输电线路T接的应用效果:在普通单回路“干”字型耐张角钢塔下侧导线横担的下方,垂直方向处再增加一组导线横担,成“十”字排列;通过增加一组导线横担,实现了在单回路耐张角钢塔上对架空输电线路中的T接问题,输电线路T接过程中,导线始终保持三角排列,角钢塔结构受力更加合理。通过合理选择线路T接方式,使设计方案更加合理,在大幅节约角钢塔占地的同时,相应工程经济技术指标更优,并使输电线路停电时间更短,施工作业更加方便。

关键词: 110kV输电线路, 单回路角钢塔, T接

Abstract: Combining with practical engineering, this article introduces the application effect of using single circuit tension angle steel towers for T connection of transmission lines in the design of 110kV overhead transmission lines. Another set of wire cross arms were added vertically below the lower side of the wire cross arm of the ordinary single circuit “干” shaped tension angle steel tower, and a “cross” arrangement was formed. By adding a set of wire cross arms, the T-connection problem in overhead transmission lines was achieved on a single circuit tension angle steel tower. During the T-connection process of transmission lines, the wires are always arranged in a triangular pattern, and the force acting on the angle steel tower structure is more reasonable. By selecting the T connection method of the transmission line reasonably, the design scheme is made more reasonable. While significantly saving the land occupied by the angle steel tower, the corresponding engineering economic and technical indicators are better, and the power outage time of the transmission line is shorter, making construction operations more convenient.

Key words: 110kV transmission line, single circuit, T connection

中图分类号: